Skip to content

Construction ID:

Floor Finishes: Carpet, Tile, Timber, Laminates, Synthetics

Construction Height:

 80 – 140¹

mm

Mass:

 110 – 140¹

kg / m²

Thermal Resistance (R-value):

 Variable²

m² K / W

Uniform Distributed Load (UDL):

2.0

kN / m²

Point Load (≥ 20 cm²):

1.0

kN

Impact Sound Reduction:

≥29³

dB

¹ Excludes floor finish.
² According to specified primary insulation.
³ Valid on concrete floors >120 mm | (DIN EN 4109: m² > 276 kg / m²).

Area of Application:

  • Ground floors or floors located above unheated rooms such as garages and basements, where Part L insulation regulation is required.
  • For upper floor construction see Construction ID: SS-U.

Additional Information:

  • For exact primary insulation requirements under the intermediate insulation please consult your insulation supplier.
  • Services such as flow and return pipes can be run within primary insulation and back filled with loose fill levelling compound.
  • 80 mm Construction Height includes 50 mm liquid screed on reduced 30 mm insulation.
  • 140 mm Construction Height includes at least 65 mm sand cement screed on typical 75 mm insulation. For additional floor loading requirements (such as 3 kN / m²) increase by a further 15 mm anhydrite or 20 mm sand cement.
  • Strict heating up protocol applies with all in screed systems.

Floor Finishes:

Carpet, Tile, Timber, Laminates, Synthetics

Construction Height:

 80 – 140¹ mm

Mass:

 110 – 140¹ kg / m²

Thermal Resistance (R-value):

 Variable² m² K / W

Uniform Distributed Load (UDL):

2.0 kN / m²

Point Load (≥ 20 cm²):

≥29³ kN

Impact Sound Reduction:

≥29³ dB

¹ Excludes floor finish.
² According to specified primary insulation.
³ Valid on concrete floors >120 mm | (DIN EN 4109: m² > 276 kg / m²).

Area of Application:

  • Ground floors or floors located above unheated rooms such as garages and basements, where Part L insulation regulation is required.
  • For upper floor construction see Construction ID: SS-U.

Additional Information:

  • For exact primary insulation requirements under the intermediate insulation please consult your insulation supplier.
  • Services such as flow and return pipes can be run within primary insulation and back filled with loose fill levelling compound.
  • 80 mm Construction Height includes 50 mm liquid screed on reduced 30 mm insulation.
  • 140 mm Construction Height includes at least 65 mm sand cement screed on typical 75 mm insulation. For additional floor loading requirements (such as 3 kN / m²) increase by a further 15 mm anhydrite or 20 mm sand cement.
  • Strict heating up protocol applies with all in screed systems.